Regulations last checked for updates: May 19, 2024

Title 48 - Federal Acquisition Regulations System last revised: May 14, 2024
852.236-79 - 852.236-79 Contractor Production Report.

As prescribed in 836.573, insert the following clause:

Contractor Production Report (APR 2019)

(a) The Contractor shall furnish to the resident engineer, for each workday, a consolidated report for the preceding workday. Reporting shall begin from date of mobilization until the date of final acceptance except for authorized holidays. VA Form 10101, Contractor Production Report, or a Contractor generated form containing the same type of information shall be signed, dated and submitted by the Contractor superintendent.

(b) Each report shall include and specifically identify at least one safety topic germane to the jobsite that day.

(End of clause) [84 FR 9974, Mar. 19, 2019]
authority: 38 U.S.C. 8127-8128 and 8151-8153; 40 U.S.C. 121(c); 41 U.S.C. 1121(c)(3); 41 U.S.C. 1303; 41 U.S.C. 1702; and 48 CFR 1.301 through 1.304
source: 73 FR 2717, Jan. 15, 2008, unless otherwise noted.
cite as: 48 CFR 852.236-79