243.204-70-4 - 243.204-70-4 Limitations on obligations.

(a) The Government shall not obligate more than 50 percent of the not-to-exceed price before definitization. However, if a contractor submits a qualifying proposal before 50 percent of the not-to-exceed price has been obligated by the Government, the limitation on obligations before definitization may be increased to no more than 75 percent (see 232.102-70 for coverage on provisional delivery payments).

(b) Obligations should be consistent with the contractor's requirements for the undefinitized period.

[75 FR 48277, Aug. 10, 2010]
authority: 41 U.S.C. 1303 and 48 CFR chapter 1
source: 56 FR 36446, July 31, 1991, unless otherwise noted.
cite as: 48 CFR 243.204-70-4