As required in § 63.8075(a) and (b), you must submit each report that applies to you on the schedule shown in the following table:
You must submit a . . .
| The report must contain . . .
| You must submit the report . . .
|
---|
1. Precompliance report | The information specified in § 63.8075(c) | At least 6 months prior to the compliance date; or for new sources, with the application for approval of construction or reconstruction.
|
2. Notification of compliance status report | The information specified in § 63.8075(d) | No later than 150 days after the compliance date specified in § 63.7995.
|
3. Compliance report | The information specified in § 63.8075(e) | Semiannually according to the requirements in § 63.8075(b).
|
4. Performance test report | The information specified in § 63.8075(f) | Within 60 days after completing each performance test according to the requirements in § 63.8075(f).
|
5. Performance evaluation report | The information specified in § 63.8075(g) | Within 60 days after completing each CMS performance evaluation according to the requirements in § 63.8075(g). |
[68 FR 69185, Dec. 11, 2003, as amended at 85 FR 49749, Aug. 14, 2020]