If the construction/reconstruction date is
| Then the owner or operator must comply with
| And the owner or operator must achieve compliance
|
---|
Group 1 POTW:
| | |
(1) After December 27, 2016 | (i) New source requirements in §§ 63.1583(b); 63.1586(b) or (c); and 63.1588 through 63.1591 | Upon initial startup.
|
(2) After December 1, 1998 but on or before December 27, 2016 | (i) New source requirements in § 63.1583(b) but instead of complying with both requirements (industrial user(s) NESHAP and the POTW standards in §§ 63.1586(b) or (c)), you must comply with the most stringent requirement
1 | Upon initial startup through October 26, 2020.
|
| (ii) New source requirements in §§ 63.1586(b) or (c); and 63.1588 through 63.1591 | On or before October 26, 2020.
|
(3) On or before December 1, 1998 | (i) Existing source requirements in §§ 63.1583(a) | By the compliance date specified in the other applicable NESHAP.
|
| (ii) Existing source requirements in §§ 63.1588 through 63.1591 | On or before October 26, 2018.
|
Group 2 POTW:
| | |
(4) After December 27, 2016 | (i) New source requirements in §§ 63.1586(b) or (c); and 63.1588 through 63.1591 | Upon initial startup.
|
(5) After December 1, 1998 but on or before December 27, 2016 | (i) New source requirements in § 63.1586(b) or (c)
1 | Upon initial startup through October 26, 2020.
|
| (ii) New source requirements in §§ 63.1586(b) or (c); and 63.1588 through 63.1591 | On or before October 26, 2020.
|
(6) On or before December 1, 1998 | (i) Existing source requirements in §§ 63.1586(a); and 63.1591(a) | On or before October 26, 2018.
|