As stated in § 63.1565(c)(1), you shall meet each requirement in the following table that applies to you.
For each new and existing
catalytic cracking unit . . .
| Subject to this emission limit for your catalyst regenerator
vent . . .
| If you must . . .
| You shall demonstrate continuous compliance by . . .
|
---|
1. Subject to the NSPS for carbon monoxide (CO) in 40 CFR 60.103, 60.100(e), or 60.102a(b)(4) | CO emissions from your catalyst regenerator vent or CO boiler serving the catalytic cracking unit must not exceed 500 ppmv (dry basis). | Continuous emission monitoring system | Collecting the hourly average CO monitoring data according to § 63.1572; and maintaining the hourly average CO concentration at or below 500 ppmv (dry basis).
|
2. Not subject to the NSPS for CO in 40 CFR 60.103 or 60.102a(b)(4) | a. CO emissions from your catalyst regenerator vent or CO boiler serving the catalytic cracking unit must not exceed 500 ppmv (dry basis). | Continuous emission monitoring system. | Same as item 1.
|
| b. CO emissions from your catalyst regenerator vent or CO boiler serving the catalytic cracking unit must not exceed 500 ppmv (dry basis). | Continuous parameter monitoring system. | Maintaining the hourly average CO concentration below 500 ppmv (dry basis).
|
| c. Visible emissions from a flare must not exceed a total of 5 minutes during any 2-hour period. | Control device-flare | On and after January 30, 2019, meeting the requirements of § 63.670. Prior to January 30, 2019, maintaining visible emissions below a total of 5 minutes during any 2-hour operating period, or meeting the requirements of § 63.670. |
[80 FR 75302, Dec. 1, 2015]