REGULATIONS
Rulings
AD/CVD
Notices
HTSUS
U.S. Code
Regs
More
Ports
About
Updates
Apps
Larger font
Smaller font
SEARCH
Sort by Rank
Titles Ascending
Titles Descending
10 per page
25 Result/page
50 Result/page
Regulations last checked for updates: May 07, 2025
Title 33 - Navigation and Navigable Waters last revised: May 05, 2025
All Titles
Title 33
Chapter I
Part 149
Subpart F - Subpart F—Design and Equipment
View all text of Subpart F [§ 149.600 - § 149.700]
§ 149.610 - What must the District Commander be notified of and when?
The District Commander must be notified of the following:
When—
The District Commander must be notified—
(a) Construction of a pipeline, platform, or single point mooring (SPM) is planned
At least 30 days before construction begins.
(b) Construction of a pipeline, platform, or SPM begins
Within 24 hours, from the date construction begins, that the lights and sound signals are in use at the construction site.
(c) A light or sound signal is changed during construction
Within 24 hours of the change.
(d) Lights or sound signals used during construction of a platform, buoy, or SPM are replaced by permanent fixtures to meet the requirements of this part
Within 24 hours of replacement.
(e) The first cargo transfer operation begins
At least 60 days before the operation.
authority:
33 U.S.C. 1504
,
1509
; DHS Delegation No. 00170.1, Revision No. 01.4
source:
USCG-1998-3884, 71 FR 57651, Sept. 29, 2006, unless otherwise noted.
cite as:
33 CFR 149.610