§ 635.307 - Coordination.

(a) The right-of-way clearance, utility, and railroad work are to be so coordinated with the physical construction that no unnecessary delay or cost for the physical construction will occur.

(b) All right-of-way clearance, utility, and railroad work performed separately from the contract for the physical construction of the project are to be accomplished in accordance with provisions of the following:

(1) 23 CFR part 140, subpart I;

(2) 23 CFR part 646, subpart B;

(3) 23 CFR 710.403; and

(4) 23 CFR part 645, subpart A.

[40 FR 17251, Apr. 18, 1975, as amended at 40 FR 25585, June 17, 1975; 64 FR 71289, Dec. 21, 1999]
authority: Sections 1525 and 1303 of Pub. L. 112–141, Sec. 1503 of Pub. L. 109–59, 119 Stat. 1144; 23 U.S.C. 101 (note), 109, 112, 113, 114, 116, 119, 128, and 315; 31 U.S.C. 6505; 42 U.S.C. 3334,4601
cite as: 23 CFR 635.307