Regulations last checked for updates: May 01, 2024

Title 48 - Federal Acquisition Regulations System last revised: Apr 25, 2024
4.804-4 - 4.804-4 Physically completed contracts.

(a) Except as provided in paragraph (b) of this section, a contract is considered to be physically completed when—

(1)(i) The contractor has completed the required deliveries and the Government has inspected and accepted the supplies;

(ii) The contractor has performed all services and the Government has accepted these services; and

(iii) All option provisions, if any, have expired; or

(2) The Government has given the contractor a notice of complete contract termination.

(b) Rental, use, and storage agreements are considered to be physically completed when—

(1) The Government has given the contractor a notice of complete contract termination; or

(2) The contract period has expired.

[48 FR 42113, Sept. 19, 1983, as amended at 72 FR 27383, May 15, 2007; 84 FR 19841, May 6, 2019]
authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113.
source: 48 FR 42113, Sept. 19, 1983, unless otherwise noted.
cite as: 48 CFR 4.804-4