Regulations last checked for updates: May 20, 2024

Title 48 - Federal Acquisition Regulations System last revised: May 14, 2024
1852.232-79 - 1852.232-79 Payment for on-site preparatory costs.

As prescribed in 1832.111-70, insert the following clause:

Payment for On-Site Preparatory Costs (SEP 1987)

Costs associated with on-site preparatory work (start-up or set-up costs) will be prorated over all work activities of a Critical Path Method (CPM) network or Progress Chart against which progress payments will be sought. Separate payment for on-site preparatory costs will not be made by the Government.

(End of clause)
authority: 51 U.S.C. 20113(a) and 48 CFR chapter 1
source: 54 FR 28340, July 5, 1989, unless otherwise noted.
cite as: 48 CFR 1852.232-79