Regulations last checked for updates: May 20, 2024

Title 48 - Federal Acquisition Regulations System last revised: May 14, 2024
1843.205 - 1843.205 Contract clauses.

As authorized in the prefaces of clauses FAR 52.243-1, Changes—Fixed Price; FAR 52.243-2, Changes—Cost Reimbursement; and FAR 52.243-4, Changes; and in the prescription at 43.205(c) for FAR 52.243-3, Changes—Time-and-Material or Labor-Hours, the period within which a contractor must assert its right to an equitable adjustment may be varied not to exceed 60 calendar days.

[65 FR 58932, Oct. 3, 2000]
authority: 51 U.S.C. 20113(a) and 48 CFR chapter 1
source: 62 FR 14022, Mar. 25, 1997, unless otherwise noted.
cite as: 48 CFR 1843.205