Regulations last checked for updates: Oct 31, 2024

Title 48 - Federal Acquisition Regulations System last revised: Oct 18, 2024
52.222-1 - 52.222-1 Notice to the Government of Labor Disputes.

As prescribed in 22.103-5(a), insert the following clause:

Notice to the Government of Labor Disputes (FEB 1997)

If the Contractor has knowledge that any actual or potential labor dispute is delaying or threatens to delay the timely performance of this contract, the Contractor shall immediately give notice, including all relevant information, to the Contracting Officer.

(End of clause) [48 FR 42478, Sept. 19, 1983, as amended at 61 FR 67426, Dec. 20, 1996]
authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 4 and 10 U.S.C. chapter 137 legacy provisions (see 10 U.S.C. 3016); and 51 U.S.C. 20113.
source: 48 FR 42478, Sept. 19, 1983, unless otherwise noted.
cite as: 48 CFR 52.222-1