You must submit a SAP, COP, or GAP and receive BOEM approval as set forth in the following table:
Before you:
| You must submit and obtain approval for your:
|
---|
(a) Conduct any site assessment activities on your commercial lease | SAP, according to §§ 585.605 through 585.613.
|
(b) Conduct any activities pertaining to construction of facilities for commercial operations on your commercial lease | COP, according to §§ 585.620 through 585.628.
|
(c) Conduct any activities on your limited lease, ROW grant, or RUE grant in any OCS area | GAP, according to §§ 585.640 through 585.648. |