Regulations last checked for updates: May 06, 2024

Title 30 - Mineral Resources last revised: Apr 24, 2024
§ 27.9 - Date for conducting tests.

The date of receipt of an application will determine the order of precedence for investigation and testing. The applicant will be notified of the date on which tests will begin.

Note:

If an assembly, subassembly, or component fails to meet any of the requirements, testing of it may be suspended and other items may be tested. However, if the cause of failure is corrected, testing will be resumed after completing such other test work as may be in progress.

[31 FR 10607, Aug. 9, 1966, as amended at 70 FR 46343, Aug. 9, 2005]
authority: 30 U.S.C. 957,961
source: 31 FR 10607, Aug. 9, 1966, unless otherwise noted.