§ 661.23 - How will a bridge project be programmed for funding once eligibility has been determined?

(a) All projects will be programmed for funding after a completed application package is received and accepted by the FHWA. At that time, the project will be acknowledged as either BIA and Tribally owned, or non-BIA owned and placed in either a PE or a construction queue.

(b) All projects will be ranked and prioritized based on the following criteria:

(1) Bridge sufficiency rating (SR);

(2) Bridge status with structurally deficient (SD) having precedence over functionally obsolete (FO);

(3) Bridges on school bus routes;

(4) Detour length;

(5) Average daily traffic; and

(6) Truck average daily traffic.

(c) Queues will carryover from fiscal year to fiscal year as made necessary by the amount of annual funding made available.

authority: 23 U.S.C. 120(j) and (k), 202, and 315; Section 1119 of the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA–LU) (Pub. L. 109–59, 119 Stat. 1144); and 49 CFR 1.48
source: 73 FR 15664, Mar. 25, 2008, unless otherwise noted.