Regulations last checked for updates: Apr 30, 2025

Title 23 - Highways last revised: Apr 18, 2025
§ 661.15 - What are the eligible activities for TTFBP funds?

TTFBP funds can be used:

(a) To carry out any planning (including safety inspection of in-service bridges), design, engineering, preconstruction, construction, and construction inspection of new or replacement TTF bridges;

(b) To replace, rehabilitate, seismically retrofit, paint, apply calcium magnesium acetate, sodium acetate/formate, or other environmentally acceptable, minimally corrosive anti-icing and deicing composition;

(c) To implement countermeasures, including scour countermeasures, for TTF bridges classified as scour critical or in poor condition, having a low load capacity, or needing geometric improvements, including multiple-pipe culverts; or

(d) To demolish the old bridge if a bridge is replaced under the TTFBP.

source: 89 FR 57082, July 12, 2024, unless otherwise noted.
cite as: 23 CFR 661.15