Regulations last checked for updates: May 18, 2024

Title 18 - Conservation of Power and Water Resources last revised: Mar 08, 2024
§ 153.23 - Reporting requirements.

Each person authorized under this part 153 that is not otherwise required to file information concerning the start of construction or modification of import/export facilities, the completion of construction or modification, and the commencement of service must file such information with the Commission within 10 days after such event. Each person, other than entities without pipeline capacity, must also report by March 1 of each year the estimated peak day capacity and actual peak day usage of its import/export facilities.

authority: 15 U.S.C. 717b,717o; E.O. 10485, 3 CFR, 1949-1953 Comp., p. 970, as amended by E.O. 12038, 3 CFR, 1978 Comp., p. 136; DOE Delegation Order No. S1-DEL-FERC-2006 (May 16, 2006)
source: Order 595, 62 FR 30446, June 4, 1997, unless otherwise noted.
cite as: 18 CFR 153.23