Cost estimates for decommissioning must be site-specific. Site-specific decommissioning cost estimates (DCEs) must account for the engineering, labor, equipment, transportation, disposal, and related charges needed to support termination of the license. They must include the costs for decontaminating structures, systems, and components and the site environs; removal of contaminated components and materials from the plant and the site environs; disposal of removed components and materials in appropriate facilities; and any other activities supporting the release of the property and termination of the license. They must also address the approach to annual adjustments required by § 53.1030. Finally, site-specific DCEs must include plans for adjusting levels of funds assured for decommissioning to demonstrate that a reasonable level of assurance will be provided that funds will be available when needed to cover the cost of decommissioning.
authority: Atomic Energy Act of 1954, secs. 11, 101, 103, 108, 122, 147, 161, 181, 182, 183, 184, 185, 186, 187, 189, 223, 234 (
42 U.S.C. 2014,
2131,
2132,
2133,
2134,
2135,
2138,
2152,
2167,
2169,
2201,
2231,
2232,
2233,
2234,
2235,
2236,
2237,
2239,
2273,
2282; Energy Reorganization Act of 1974, secs. 201, 202, 206, 211 (
42 U.S.C. 5841,
5842,
5846,
5851; Nuclear Waste Policy Act of 1982, sec. 306 (
42 U.S.C. 10226); National Environmental Policy Act of 1969 (
42 U.S.C. 4332);
44 U.S.C. 3504 note; Pub. L. 115-439, 132 Stat. 5571
source: 91 FR 15794, Mar. 30, 2026, unless otherwise noted.
cite as: 10 CFR 53.1020