Regulations last checked for updates: May 18, 2024

Title 7 - Agriculture last revised: Nov 16, 2024
§ 1970.51 - Applying CEs.

(a) The actions listed in §§ 1970.53 through 1970.55 are classes of actions that the Agency has determined do not individually or cumulatively have a significant effect on the human environment (referred to as “categorical exclusions” or CEs).

(1) Actions listed in § 1970.53 do not normally require applicants to submit environmental documentation with their applications. However, these applicants may be required to provide environmental information at the Agency's request.

(2) Actions listed in § 1970.54 normally require the submission of an environmental report (ER) by an applicant to allow the Agency to determine whether extraordinary circumstances (as defined in § 1970.52(a)) exist. When the Agency determines that extraordinary circumstances exist, an EA or EIS, as appropriate, will be required and, in such instances, applicants may be required to provide additional environmental information later at the Agency's request.

(3) Actions listed in § 1970.55 relate to financial assistance whereby the applicant is a primary recipient of a multi-tier program providing financial assistance to secondary or ultimate recipients without specifying the use of such funds for eligible actions at the time of initial application and approval. The decision to approve or fund such initial proposals has no discernible environmental effects and is therefore categorically excluded provided the primary recipient enters into an agreement with the Agency for future reviews. The primary recipient is limited to making the Agency's financial assistance available to secondary recipients for the types of projects specified in the primary recipient's application. Second-tier funding of proposals to secondary or ultimate recipients will be screened for extraordinary circumstances by the primary recipient and monitored by the Agency. If the primary recipient determines that extraordinary circumstances exist on any second-tier proposal, it must be referred to the Agency for the appropriate level of review under this part in accordance with subparts C and D.

(b) To find that a proposal is categorically excluded, the Agency must determine the following:

(1) The proposal fits within a class of actions that is listed in §§ 1970.53 through 1970.55;

(2) There are no extraordinary circumstances related to the proposal (see § 1970.52); and

(3) The proposal is not “connected” to other actions with potentially significant impacts (see 40 CFR 1508.25(a)(1)) or is not considered a “cumulative action” (see 40 CFR 1508.25(a)(2)), and is not precluded by 40 CFR 1506.1.

(c) A proposal that consists of more than one action may be categorically excluded only if all components of the proposed action are eligible for a CE.

(d) If, at any time during the environmental review process, the Agency determines that the proposal does not meet the criteria listed in §§ 1970.53 through 1970.55, an EA or EIS, as appropriate, will be required.

(e) Failure to achieve compliance with this part will postpone further consideration of an applicant's proposal until such compliance is achieved or the applicant withdraws the proposal. If compliance is not achieved, the Agency will deny the request for financial assistance.

§ 1970.52 - Extraordinary circumstances.

(a) Extraordinary circumstances are unique situations presented by specific proposals, such as characteristics of the geographic area affected by the proposal, scientific controversy about the environmental effects of the proposal, uncertain effects or effects involving unique or unknown risks, and unresolved conflicts concerning alternate uses of available resources within the meaning of section 102(2)(E) of NEPA. In the event of extraordinary circumstances, a normally excluded action will be the subject of an additional environmental review by the Agency to determine the potential of the Agency action to cause any significant adverse environmental effect, and could, at the Agency's sole discretion, require an EA or an EIS, prepared in accordance with subparts C or D of this part, respectively.

(b) Significant adverse environmental effects that the Agency considers to be extraordinary circumstances include, but are not limited to:

(1) Any violation of applicable Federal, state, or local statutory, regulatory, or permit requirements for environment, safety, and health.

(2) Siting, construction, or major expansion of Resource Conservation and Recovery Act permitted waste storage, disposal, recovery, or treatment facilities (including incinerators), even if the proposal includes categorically excluded waste storage, disposal, recovery, or treatment actions.

(3) Any proposal that is likely to cause uncontrolled or unpermitted releases of hazardous substances, pollutants, contaminants, or petroleum and natural gas products.

(4) An adverse effect on the following environmental resources:

(i) Historic properties;

(ii) Federally listed threatened or endangered species, critical habitat, Federally proposed or candidate species;

(iii) Wetlands (Those actions that propose to convert or propose new construction in wetlands will require consideration of alternatives to avoid adverse effects and unwarranted conversions of wetlands. For actions involving linear utility infrastructure where utilities are proposed to be installed in existing, previously disturbed rights-of-way or that are authorized under applicable Clean Water Act, Section 404 nationwide permits will not require the consideration of alternatives. Those actions that require Section 404 individual permits would create an extraordinary circumstance);

(iv) Floodplains (those actions that introduce fill or structures into a floodplain or propose substantial improvements to structures within a floodplain will require consideration of alternatives to avoid adverse effects and incompatible development in floodplains. Actions that do not adversely affect the hydrologic character of a floodplain, such as buried utility lines or subsurface pump stations, would not create an extraordinary circumstance; or purchase of existing structures within the floodplain will not create an extraordinary circumstance but may require consideration of alternatives to avoid adverse effects and incompatible development in floodplains when determined appropriate by the Agency);

(v) Areas having formal Federal or state designations such as wilderness areas, parks, or wildlife refuges; wild and scenic rivers; or marine sanctuaries;

(vi) Special sources of water (such as sole source aquifers, wellhead protection areas, and other water sources that are vital in a region);

(vii) Coastal barrier resources or, unless exempt, coastal zone management areas; and

(viii) Coral reefs.

(5) The existence of controversy based on effects to the human environment brought to the Agency's attention by a Federal, tribal, state, or local government agency.

§ 1970.53 - CEs involving no or minimal disturbance without an environmental report.

The CEs in this section are for proposals for financial assistance that involve no or minimal alterations in the physical environment and typically occur on previously disturbed land. These actions normally do not require an applicant to submit environmental documentation with the application. However, based on the review of the project description, the Agency may request additional environmental documentation from the applicant at any time, specifically if the Agency determines that extraordinary circumstances may exist. In accordance with Section 106 of the National Historic Preservation Act (54 U.S.C. 300101 et seq.) and its implementing regulations under 36 CFR 800.3(a), the Agency has determined that the actions in this section are undertakings, and in accordance with 36 CFR 800.3(a)(1) has identified those undertakings for which no further review under 36 CFR part 800 is required because they have no potential to cause effects to historic properties. In accordance with section 7 of the Endangered Species Act (16 U.S.C. 1531 et seq.) and its implementing regulations at 50 CFR part 402, the Agency has determined that the actions in this section are actions for purposes of the Endangered Species Act, and in accordance with 50 CFR 402.06 has identified those actions for which no further review under 50 CFR part 402 is required because they will have no effect to listed threatened and endangered species.

(a) Routine financial actions. The following are routine financial actions and, as such, are classified as categorical exclusions identified in paragraphs (a)(1) through (7) of this section.

(1) Financial assistance for the purchase, transfer, lease, or other acquisition of real property when no or minimal change in use is reasonably foreseeable.

(i) Real property includes land and any existing permanent or affixed structures.

(ii) “No or minimal change in use is reasonably foreseeable” means no or only a small change in use, capacity, purpose, operation, or design is expected where the foreseeable type and magnitude of impacts would remain essentially the same.

(2) Financial assistance for the purchase, transfer, or lease of personal property or fixtures where no or minimal change in operations is reasonably foreseeable. These include:

(i) Approval of minimal expenditures not affecting the environment such as contracts for long lead-time equipment and purchase options by applicants under the terms of 40 CFR 1506.1(d) and 7 CFR 1970.12;

(ii) Acquisition of end-user equipment and programming for telecommunication distance learning;

(iii) Purchase, replacement, or installation of equipment necessary for the operation of an existing facility (such as Supervisory Control and Data Acquisition Systems (SCADA), energy management or efficiency improvement systems (including heat rate efficiency), replacement or conversion to enable use of renewable fuels, standby internal combustion electric generators, battery energy storage systems, and associated facilities for the primary purpose of providing emergency power);

(iv) Purchase of vehicles (such as those used in business, utility, community, or emergency services operations);

(v) Purchase of existing water rights where no associated construction is involved;

(vi) Purchase of livestock and essential farm equipment, including crop storing and drying equipment; and

(vii) Purchase of stock in an existing enterprise to obtain an ownership interest in that enterprise.

(3) Financial assistance for operating (working) capital for an existing operation to support day-to-day expenses.

(4) Sale or lease of Agency-owned real property, if the sale or lease of Agency-owned real property will have no or minimal construction or change in current operations in the foreseeable future.

(5) The provision of additional financial assistance for cost overruns where the purpose, operation, location, and design of the proposal as originally approved has not been substantially changed.

(6) Rural Business Investment Program (7 U.S.C. 1989 and 2009cc et seq.) actions as follows:

(i) Non-leveraged program actions that include licensing by USDA of Rural Business Investment Companies (RBIC); or

(ii) Leveraged program actions that include licensing by USDA of RBIC and Federal financial assistance in the form of technical grants or guarantees of debentures of an RBIC, unless such Federal assistance is used to finance construction or development of land.

(7) A guarantee provided to a guaranteed lender for the sole purpose of refinancing outstanding bonds or notes or a guarantee provided to the Federal Financing Bank pursuant to Section 313A(a) of the Rural Electrification Act of 1936 for the purpose of:

(i) Refinancing existing debt instruments of a lender organized on a not-for-profit basis; or

(ii) Prepaying outstanding notes or bonds made to or guaranteed by the Agency.

(b) Information gathering and technical assistance. The following are CEs for financial assistance, identified in paragraphs (b)(1) through (3) of this section.

(1) Information gathering, data analysis, document preparation, real estate appraisals, environmental site assessments, and information dissemination. Examples of these actions are:

(i) Information gathering such as research, literature surveys, inventories, and audits;

(ii) Data analysis such as computer modeling;

(iii) Document preparation such as strategic plans; conceptual designs; management, economic, planning, or feasibility studies; energy audits or assessments; environmental analyses; and survey and analyses of accounts and business practices; and

(iv) Information dissemination such as document mailings, publication, and distribution; and classroom training and informational programs.

(2) Technical advice, training, planning assistance, and capacity building. Examples of these actions are:

(i) Technical advice, training, planning assistance such as guidance for cooperatives and self-help housing group planning; and

(ii) Capacity building such as leadership training, strategic planning, and community development training.

(3) Site characterization, environmental testing, and monitoring where no significant alteration of existing ambient conditions would occur. This includes, but is not limited to, air, surface water, groundwater, wind, soil, or rock core sampling; installation of monitoring wells; and installation of small-scale air, water, or weather monitoring equipment.

(c) Minor construction proposals. The following are CEs that apply to financial assistance for minor construction proposals:

(1) Minor amendments or revisions to previously approved projects provided such activities do not alter the purpose, operation, geographic scope, or design of the project as originally approved;

(2) Repair, upgrade, or replacement of equipment in existing structures for such purposes as improving habitability, energy efficiency (including heat rate efficiency), replacement or conversion to enable use of renewable fuels, pollution prevention, or pollution control;

(3) Any internal modification or minimal external modification, restoration, renovation, maintenance, and replacement in-kind to an existing facility or structure;

(4) Construction of or substantial improvement to a single-family dwelling, or a Rural Housing Site Loan project or multi-family housing project serving up to four families and affecting less than 10 acres of land;

(5) Siting, construction, and operation of new or additional water supply wells for residential, farm, or livestock use;

(6) Replacement of existing water and sewer lines within the existing right-of-way and as long as the size of pipe is either no larger than the inner diameter of the existing pipe or is an increased diameter as required by Federal or state requirements. If a larger pipe size is required, applicants must provide a copy of written administrative requirements mandating a minimum pipe diameter from the regulatory agency with jurisdiction;

(7) Modifications of an existing water supply well to restore production in existing commercial well fields, if there would be no drawdown other than in the immediate vicinity of the pumping well, no resulting long-term decline of the water table, and no degradation of the aquifer from the replacement well;

(8) New utility service connections to individual users or construction of utility lines or associated components where the applicant has no control over the placement of the utility facilities; and

(9) Conversion of land in agricultural production to pastureland or forests, or conversion of pastureland to forest.

(d) Energy or telecommunication proposals. The following are CEs that apply to financial assistance for energy or telecommunication proposals:

(1) Upgrading or rebuilding existing telecommunication facilities (both wired and wireless) or addition of aerial cables for communication purposes to electric power lines that would not affect the environment beyond the previously-developed, existing rights-of-way;

(2) Burying new facilities for communication purposes in previously developed, existing rights-of-way and in areas already in or committed to urbanized development or rural settlements whether incorporated or unincorporated that are characterized by high human densities and within contiguous, highly disturbed environments with human-built features. Covered actions include associated vaults and pulling and tensioning sites outside rights-of-way in nearby previously disturbed or developed land;

(3) Changes to electric transmission lines that involve pole replacement or structural components only where either the same or substantially equivalent support structures at the approximate existing support structure locations are used;

(4) Phase or voltage conversions, reconductoring, upgrading, or rebuilding of existing electric distribution lines that would not affect the environment beyond the previously developed, existing rights-of-way. Includes pole replacements but does not include overhead-to-underground conversions;

(5) Collocation of telecommunications equipment on existing infrastructure and deployment of distributed antenna systems and small cell networks provided the latter technologies are not attached to and will not cause adverse effects to historic properties;

(6) Siting, construction, and operation of small, ground source heat pump systems that would be located on previously developed land;

(7) Siting, construction, and operation of small solar electric projects or solar thermal projects to be installed on or adjacent to an existing structure and that would not affect the environment beyond the previously developed facility area and are not attached to and will not cause adverse effects to historic properties;

(8) Siting, construction, and operation of small biomass projects, such as animal waste anaerobic digesters or gasifiers, that would use feedstock produced on site (such as a farm where the site has been previously disturbed) and supply gas or electricity for the site's own energy needs with no or only incidental export of energy;

(9) Construction of small standby electric generating facilities with a rating of one average megawatt (MW) or less, and associated facilities, for the purpose of providing emergency power for or startup of an existing facility;

(10) Additions or modifications to electric transmission facilities that would not affect the environment beyond the previously developed facility area including, but not limited to, switchyard rock, grounding upgrades, secondary containment projects, paving projects, seismic upgrading, tower modifications, changing insulators, and replacement of poles, circuit breakers, conductors, transformers, and crossarms; and

(11) Safety, environmental, or energy efficiency (including heat rate efficiency) improvements within an existing electric generation facility, including addition, replacement, or upgrade of facility components (such as precipitator, baghouse, or scrubber installations), that do not result in a change to the design capacity or function of the facility and do not result in an increase in pollutant emissions, effluent discharges, or waste products.

(e) Emergency situations. Repairs made because of an emergency situation to return to service damaged facilities of an applicant's utility system or other actions necessary to preserve life and control the immediate impacts of the emergency.

(f) Promulgation of rules or formal notices. The promulgation of rules or formal notices for policies or programs that are administrative or financial procedures for implementing Agency assistance activities.

(g) Agency proposals for legislation. Agency proposals for legislation that have no potential for significant environmental impacts because they would allow for no or minimal construction or change in operations.

(h) Administrative actions. Agency procurement activities for goods and services; routine facility operations; personnel actions, including but not limited to, reduction in force or employee transfers resulting from workload adjustments, and reduced personnel or funding levels; and other such management actions related to the operation of the Agency.

§ 1970.54 - CEs involving small-scale development with an environmental report.

The CEs in this section are for proposals for financial assistance that require an applicant to submit an ER with their application to facilitate Agency determination of extraordinary circumstances. At a minimum, the ER will include a complete description of all components of the applicant's proposal and any connected actions, including its specific location on detailed site plans as well as location maps equivalent to a U.S. Geological Survey (USGS) quadrangle map; and information from authoritative sources acceptable to the Agency confirming the presence or absence of sensitive environmental resources in the area that could be affected by the applicant's proposal. The ER submitted must be accurate, complete, and capable of verification. The Agency may request additional information as needed to make an environmental determination. Failure to submit the required environmental report will postpone further consideration of the applicant's proposal until the ER is submitted, or the Agency may deny the request for financial assistance. The Agency will review the ER and determine if extraordinary circumstances exist. The Agency's review may determine that classification as an EA or an EIS is more appropriate than a CE classification.

(a) Small-scale site-specific development. The following CEs apply to proposals where site development activities (including construction, expansion, repair, rehabilitation, or other improvements) for rural development purposes would impact not more than 10 acres of real property and would not cause a substantial increase in traffic. These CEs are identified in paragraphs (a)(1) through (a)(9) of this section. This paragraph does not apply to new industrial proposals (such as ethanol and biodiesel production facilities) or those classes of action listed in §§ 1970.53, 1970.101, or 1970.151.

(1) Multi-family housing and Rural Housing Site Loans.

(2) Business development.

(3) Community facilities such as municipal buildings, libraries, security services, fire protection, schools, and health and recreation facilities.

(4) Infrastructure to support utility systems such as water or wastewater facilities; headquarters, maintenance, equipment storage, or microwave facilities; and energy management systems. This does not include proposals that either create a new or relocate an existing discharge to or a withdrawal from surface or ground waters, or cause substantial increase in a withdrawal or discharge at an existing site.

(5) Installation of new, commercial-scale water supply wells and associated pipelines or water storage facilities that are required by a regulatory authority or standard engineering practice as a backup to existing production well(s) or as reserve for fire protection.

(6) Construction of telecommunications towers and associated facilities, if the towers and associated facilities are 450 feet or less in height and would not be in or visible from an area of documented scenic value.

(7) Repair, rehabilitation, or restoration of water control, flood control, or water impoundment facilities, such as dams, dikes, levees, detention reservoirs, and drainage ditches, with minimal change in use, size, capacity, purpose, operation, location, or design from the original facility.

(8) Installation or enlargement of irrigation facilities on an applicant's land, including storage reservoirs, diversion dams, wells, pumping plants, canals, pipelines, and sprinklers designed to irrigate less than 80 acres.

(9) Replacement or restoration of irrigation facilities, including storage reservoirs, diversion dams, wells, pumping plants, canals, pipelines, and sprinklers, with no or minimal change in use, size, capacity, or location from the original facility(s).

(10) Vegetative biomass harvesting operations of no more than 15 acres, provided any amount of land involved in harvesting is to be conducted managed on a sustainable basis and according to a Federal, state, or other governmental unit approved management plan.

(b) Small-scale corridor development. The following CEs apply to financial assistance for:

(1) Construction or repair of roads, streets, and sidewalks, including related structures such as curbs, gutters, storm drains, and bridges, in an existing right-of-way with minimal change in use, size, capacity, purpose, or location from the original infrastructure;

(2) Improvement and expansion of existing water, waste water, and gas utility systems:

(i) Within one mile of currently served areas irrespective of the percent of increase in new capacity, or

(ii) Increasing capacity not more than 30 percent of the existing user population;

(3) Replacement of utility lines where road reconstruction undertaken by non-Agency applicants requires the relocation of lines either within or immediately adjacent to the new road easement or right-of-way; and

(4) Installation of new linear telecommunications facilities and related equipment and infrastructure.

(c) Small-scale energy proposals. The following CEs apply to financial assistance for:

(1) Construction of electric power substations (including switching stations and support facilities) or modification of existing substations, switchyards, and support facilities;

(2) Construction of electric power lines and associated facilities designed for or capable of operation at a nominal voltage of either:

(i) Less than 69 kilovolts (kV);

(ii) Less than 230 kV if no more than 25 miles of line are involved; or

(iii) 230 kV or greater involving no more than three miles of line, but not for the integration of major new generation resources into a bulk transmission system;

(3) Reconstruction (upgrading or rebuilding) or minor relocation of existing electric transmission lines (230 kV or less) 25 miles in length or less to enhance environmental and land use values or to improve reliability or access. Such actions include relocations to avoid right-of-way encroachments, resolve conflict with property development, accommodate road/highway construction, allow for the construction of facilities such as canals and pipelines, or reduce existing impacts to environmentally sensitive areas;

(4) Repowering or uprating modifications or expansion of an existing unit(s) up to a rating of 50 average MW at electric generating facilities in order to maintain or improve the efficiency, capacity, or energy output of the facility. Any air emissions from such activities must be within the limits of an existing air permit;

(5) Installation of new generating units or replacement of existing generating units at an existing hydroelectric facility or dam which results in no change in the normal maximum surface area or normal maximum surface elevation of the existing impoundment. All supporting facilities and new related electric transmission lines 10 miles in length or less are included;

(6) Installation of a heat recovery steam generator and steam turbine with a rating of 200 average MW or less on an existing electric generation site for the purpose of combined cycle operations. All supporting facilities and new related electric transmission lines 10 miles in length or less are included;

(7) Construction of small electric generating facilities (except geothermal and solar electric projects), including those fueled with wind or biomass, with a rating of 10 average MW or less. All supporting facilities and new related electric transmission lines 10 miles in length or less are included;

(8) Siting, construction, and operation of small biomass projects (except small electric generating facilities projects fueled with biomass) producing not more than 3 million gallons of liquid fuel or 300,000 million british thermal units annually, developed on up 10 acres of land;

(9) Geothermal electric power projects or geothermal heating or cooling projects developed on up to 10 acres of land and including installation of one geothermal well for the production of geothermal fluids for direct use application (such as space or water heating/cooling) or for power generation. All supporting facilities and new related electric transmission lines 10 miles in length or less are included;

(10) Solar electric projects or solar thermal projects developed on up to 10 acres of land including all supporting facilities and new related electric transmission lines 10 miles in length or less;

(11) Distributed resources of any capacity located at or adjacent to an existing landfill site or wastewater treatment facility that is powered by refuse-derived fuel. All supporting facilities and new related electric transmission lines 10 miles in length or less are included;

(12) Small conduit hydroelectric facilities having a total installed capacity of not more than 5 average MW using an existing conduit such as an irrigation ditch or a pipe into which a turbine would be placed for the purpose of electric generation. All supporting facilities and new related electric transmission lines 10 miles in length or less are included; and

(13) Modifications or enhancements to existing facilities or structures that would not substantially change the footprint or function of the facility or structure and that are undertaken for the purpose of improving energy efficiency (including heat rate efficiency), promoting pollution prevention or control, safety, reliability, or security. This includes, but is not limited to, retrofitting existing facilities to produce biofuels and replacing fossil fuels used to produce heat or power in biorefineries with renewable biomass. This also includes installation of fuel blender pumps and associated changes within an existing fuel facility.

§ 1970.55 - CEs for multi-tier actions.

The CEs in this section apply solely to providing financial assistance to primary recipients in multi-tier action programs.

(a) The Agency's approval of financial assistance to a primary recipient in a multi-tier action program is categorically excluded under this section only if the primary recipient agrees in writing to:

(1) Conduct a screening of all proposed uses of funds to determine whether each proposal that would be funded or financed falls within § 1970.53 or § 1970.54 as a categorical exclusion;

(2) Obtain sufficient information to make an evaluation of those proposals listed in § 1970.53 and prepare an ER for proposals under § 1970.54 to determine if extraordinary circumstances (as described in § 1970.52) are present;

(3) Document and maintain its conclusions regarding the applicability of a CE in its official records for Agency verification; and

(4) Refer all proposals that do not meet listed CEs in § 1970.53 or § 1970.54, and proposals that may have extraordinary circumstances (as described in § 1970.52) to the Agency for further review in accordance with this part.

(b) The primary recipient's compliance with this section will be monitored and verified in Agency compliance reviews and other required audits. Failure by a primary recipient to meet the requirements of this section will result in penalties that may include written warnings, withdrawal of Agency financial assistance, suspension from participation in Agency programs, or other appropriate action.

(c) Nothing in this section is intended to delegate the Agency's responsibility for compliance with this part. The Agency will continue to maintain ultimate responsibility for and control over the environmental review process in accordance with this part.

§§ 1970.56-1970.100 - §[Reserved]
authority: 7 U.S.C. 6941
source: 81 FR 11032, Mar. 2, 2016, unless otherwise noted.
cite as: 7 CFR 1970.53