The contracting officer must insert the clause at 3452.242-70 (Litigation and claims) in all solicitations and resultant cost-reimbursement contracts.
The contracting officer must insert the clause at 3452.242-71 (Notice to the Government of delays) in all solicitations and contracts other than purchase orders.
source: 88 FR 60542, Sept. 1, 2023, unless otherwise noted.
cite as: 48 CFR 3442.7001