Regulations last checked for updates: Feb 06, 2026

Title 18 - Conservation of Power and Water Resources last revised: Feb 02, 2026
§ 1318.100 - Determining when NEPA applies.

(a) At the earliest possible time, TVA will determine whether a proposed action requires an environmental review under NEPA and, if so, the level of environmental review.

(b) TVA will determine that NEPA does not apply to a proposed agency action when:

(1) The activities or decision do not result in final agency action under the Administrative Procedure Act, see 5 U.S.C. 704,or;

(2) The proposed activity or decision is exempted from NEPA by law;

(3) Compliance with NEPA would clearly and fundamentally conflict with the requirements of another provision of law;

(4) In circumstances where Congress by statute has prescribed decisional criteria with sufficient completeness and precision such that TVA retains no residual discretion to alter its action based on the consideration of environmental factors, then that function of TVA is nondiscretionary within the meaning of NEPA sec. 106(a)(4) and/or sec. 111(10)(B)(vii) (42 U.S.C. 4336(a)(4) and 4336e(10)(B)(vii), respectively), and NEPA does not apply to the action in question;

(5) The proposed action is an action for which another statute's requirements serve the function of agency compliance with the Act; or

(6) The proposed action is not a “major Federal action.” The terms “major” and “federal action,” each have independent force. NEPA applies only when both of these two criteria are met. Such a determination is inherently bound up in the facts and circumstances of each individual situation, and is thus reserved to the judgment of TVA in each instance.

(7) NEPA does not apply to “non-Federal actions.” Therefore, under the terms of the statue, NEPA does not apply to actions with no or minimal Federal funding, or with no or minimal Federal involvement where a Federal agency cannot control the outcome of the project. NEPA sec. 111(10)(B)(i), 42 U.S.C. 4336e(10)(B)(i). A but-for causal relationship is insufficient to make an agency responsible for a particular action under NEPA. By the same token, minimal Federal funding or involvement does not by itself convert that action into a Federal action within the meaning of the language of the statute.

(c) The issuance or update of TVA's NEPA procedures is not subject to NEPA review.

(d) In determining whether NEPA applies to a proposed agency action, TVA will consider only the action or project at hand.

§ 1318.101 - Determining the appropriate level of NEPA review.

(a) If TVA determines under § 1318.100 that NEPA applies to a proposed action or decision, TVA will then determine the appropriate level of NEPA review in the following sequence and manner. At all steps in the following process, TVA will consider the proposed action or project at hand and its effects.

(1) If TVA has established, or adopted pursuant to NEPA sec. 109, 42 U.S.C. 4336c,a,TVA,if,pursuant.

(2) If another agency has already established a categorical exclusion that covers the proposed action, TVA will consider whether to adopt that exclusion pursuant to § 1318.200(d) so that it can be applied to the proposed action at issue, and to future actions or decisions of that type.

(3) If the proposed action warrants the establishment of a new categorical exclusion, or the revision of an existing categorical exclusion, pursuant to § 1318.200(c), TVA will consider whether to establish or revise, and then apply the categorical exclusion to the proposed action pursuant to subpart C of this part.

(4) If TVA cannot apply a categorical exclusion to the proposed action consistent with paragraphs (a)(1) through (3) of this section, TVA will consider the proposed action's reasonably foreseeable effects consistent with paragraph (b) of this section, and then will:

(i) if the proposed action is not likely to have reasonably foreseeable significant effects or the significance of the effects is unknown, develop an EA, as described in subpart D of this part; or

(ii) if the proposed action is likely to have reasonably foreseeable significant effects, develop an EIS, as described in subpart E of this part.

(b) When considering whether the reasonably foreseeable effects of the proposed action are significant, TVA will analyze the potentially affected environment and degree of the effects of the proposed action. TVA may use any reliable data source and will not undertake new research unless it is essential to evaluating alternatives and the cost and time of obtaining it are not unreasonable.

(1) In considering the potentially affected environment, TVA may consider, as appropriate to the specific proposed action, the affected area and its resources.

(2) In considering the degree of the effects, TVA may consider the following, as appropriate to the specific proposed action:

(i) Both short- and long-term effects.

(ii) Both beneficial and adverse effects.

(iii) Effects on public health and safety.

(iv) Economic effects

(v) Effects on the quality of life of the American people.

§ 1318.102 - Determination of NEPA Adequacy.

TVA will determine whether a proposed action is already evaluated by an existing NEPA review, including a programmatic or generic review. In making a determination, TVA will evaluate and document whether the following conditions are met:

(a) The new proposed action is substantially similar to an action previously analyzed in an existing environmental document(s);

(b) The reasonably foreseeable environmental effects that would result from the new proposed action are similar to those analyzed in an existing environmental document(s); and

(c) Any new information or circumstances relevant to environmental concerns would not substantially change the analysis in an existing environmental document(s).

§ 1318.103 - Supplements.

(a) After completion of an environmental document, if TVA makes substantial changes in the proposed action that are relevant to environmental concerns or there is substantial new circumstances or information about the significance of the adverse effects that bear on the proposed action or its impact, and important components of the proposed action remain to be implemented, TVA will determine how the environmental document should be supplemented or modified. TVA may supplement an environmental document by issuing a new document that addresses changes in the proposed action or new circumstances or information or may modify the existing document so that revisions and edits to the original document are apparent. A supplemented or modified environmental document will be published.

(b) After completion of an environmental document, if TVA determines that changes to the proposed action that are relevant to environmental concerns are not substantial or new circumstances or information are not significant or relevant to environmental concerns, and therefore supplemental analysis is not warranted, TVA will document this determination consistent with § 1318.102.

§ 1318.104 - Reliance on existing environmental documents.

(a) TVA may rely on another Federal agency's EA or EIS (including an EA or EIS prepared by a Tribal, State, or local agency on behalf of a Federal agency), or a portion thereof, if TVA determines that TVA's proposed action is substantially the same or similar to the other agency's action, and the other agency's document meets the standards for an adequate statement or assessment under these procedures.

(b) In making this determination, TVA will consider whether the scope and analyses in the other agency's EA or EIS adequately address the TVA action. TVA will cite, briefly describe the content and relevance to the environmental document, and may make modifications that are necessary to render the relied-upon document, or portion thereof, fit for fulfilling NEPA analytic requirements for the action at hand. TVA will publish this determination and the EA or EIS relied upon and notify affected Federal, Tribal, State, and local agencies and other interested entities.

(c) TVA may supplement another agency's EA or EIS in accordance with § 1318.103.

§ 1318.105 - Lead and cooperating agency determinations.

(a) As soon as practicable after the determination is made to prepare an EA or EIS, TVA will determine whether inviting other Federal, Tribal, State, or local agencies to participate in the preparation of the EA or EIS as lead, joint lead, or cooperating agencies is appropriate (NEPA sec. 107(a), 42 U.S.C. 4336a,and. 111, 42 U.S.C. 4336e). TVA will typically serve as the lead Federal agency for TVA actions. Any designation of lead federal agency will be made in accordance with NEPA sec. 107, U.S.C. 4336a.

(b) If TVA is participating with other Federal agencies in a NEPA review, TVA will cooperate with the other Federal agency(ies) to designate agency roles (e.g., lead agency, joint lead agency, cooperating agency).

(c) When participating with other Federal agencies, TVA will, to the extent practicable, work with the other Federal, Tribal, State, or local agencies to prepare a single environmental document.

§ 1318.106 - Schedule for the NEPA process.

(a) Once TVA has made a determination of the level of NEPA review, TVA, and if applicable, project sponsors or other participating agencies, will establish a schedule for the completion of the environmental document, consistent with deadlines identified in NEPA sec. 107(g), 42 U.S.C. 4336a(g). Prior to establishing the schedule, TVA will review for completeness any information, data, materials, and/or any applications or agreements that are necessary to determine the level of NEPA review.

(b) TVA will address in the schedule, as appropriate, any concurrent and integrated surveys and studies required by other applicable environmental review laws and Executive Orders, including but not limited to the National Historic Preservation Act of 1966 (54 U.S.C. 300101 et seq.) and the Endangered Species Act of 1973 (16 U.S.C. 1531 et seq.).

(c) As the Supreme Court has repeatedly held, NEPA is governed by a “rule of reason.” Congress supplied the measure of that reason in the 2023 revision of NEPA by setting the deadlines in NEPA sec. 107(g), 42 U.S.C. 4336a(g). These deadlines indicate Congress's determination that an agency has presumptively spent a reasonable amount of time on analysis and the document should issue, absent very unusual circumstances. In such circumstances, an extension will be given only for such time as is necessary to complete the analysis.

(1) TVA will complete an EIS not later than the date that is 2 years after the sooner of the date on which TVA determines that NEPA requires the preparation of an EIS with response to the proposal; the date on which TVA notifies the applicant that the application to establish a right-of-way for the proposal is complete; and the date on which TVA issues a notice of intent to prepare the EIS. (42 U.S.C. 4336a(g)(1)(A))

(2) TVA will complete an EA not later than the date that is 1 year after the sooner of the date on which TVA determines that NEPA requires the preparation of an EA with response to the proposal; the date on which TVA notifies the applicant that the application to establish a right-of-way for such action is complete; and the date on which TVA issues a notice of intent to prepare the EA for the proposal. (42 U.S.C. 4336a(g)(1)(B))

(3) TVA will calculate EIS or EA schedules from the applicable start date to the date TVA publishes the EIS or a finding of no significant impact as the end date. Where TVA has prepared an EA that results in a decision to prepare an EIS, TVA will use the start date for the EA as the start date for the EIS unless it exercises its discretion to determine otherwise by direction of the TVA official responsible for NEPA.

(4) The EIS or EA will publish (unless the deadline is extended pursuant to the provision below) on the day the deadline elapses, in as substantially complete form as is possible.

(5) TVA will document the start and completion dates of each EIS or EA to assist TVA in tracking the schedule and preparing a report to congressional committees required by NEPA § 107(h), 42 U.S.C. 4336a(h).

(d) If TVA determines it is not able to meet the deadline prescribed by NEPA sec. 107(g)(1), 42 U.S.C. 4336a(g)(1), TVA will consult with the applicant, if any, pursuant to NEPA sec. 107(g)(2), 42 U.S.C. 4336a(g)(2). After such consultation, if needed, and for cause stated, TVA may establish a new deadline and appropriately document the cause. Cause for establishing a new deadline is only established if the EIS or EA is so incomplete, at the time at which TVA determines it is not able to meet the statutory deadline, that issuance would, in TVA's view, result in an inadequate analysis. Such new deadline must provide only so much additional time as is necessary to complete such EIS or EA. The announcement of the new deadline will specify the reason why the EIS or EA was not able to be completed under the statutory deadline and whether the applicant consented to the new deadline.

(e) When the EIS or EA is published, a responsible official will certify (and the certification will be incorporated into the EIS or EA) that the resulting EIS or EA represents TVA's good-faith effort to fulfill NEPA's requirements within the Congressional timeline; that such effort is substantially complete; and that, in the TVA's expert opinion, it has thoroughly considered the factors mandated by NEPA; and that, in TVA's judgment, the analysis contained therein is adequate to inform and reasonably explain TVA's final decision regarding the proposed federal action.

§ 1318.107 - Scoping process.

(a) TVA will publish a notice of intent for an EIS and request public comment on the proposed action and alternatives.

(b) TVA may use the scoping process to identify for analysis in an EA or EIS the substantive issues that meaningfully inform the consideration of environmental effects and reasonable alternatives to be considered. Scoping may also identify non-substantive issues that do not require analysis and/or alternatives that are determined not to be reasonable. Scoping may include work conducted prior to publication of the notice of intent or formal initiation of the NEPA process, including prior public engagement to identify issues and alternatives that may inform the eventual alternatives analyzed.

(c) The scoping process may include interagency scoping sessions to coordinate an action with and obtain inputs from other interested agencies (including likely affected Federal, Tribal, State, and local agencies).

(d) On the basis of input received during the scoping process, TVA will determine whether to modify the scope, schedule, or the type of environmental document.

authority: 16 U.S.C. 831
source: 85 FR 17458, Mar. 27, 2020, as amended at 91 FR 2475, Jan. 21, 2026, unless otherwise noted.
cite as: 18 CFR 1318.101