| Service—processing of the following:
| Fee amount
| 30 CFR citation
|
|---|
| (1) Suspension of Operations/Suspension of Production (SOO/SOP) Request | $2,469 | § 250.171(e).
|
| (2) Deepwater Operations Plan (DWOP) Process:
| | |
| (i) Project Conceptual Plan | $2,697 | 250.226.
|
| (ii) New or Unusual Technology Conceptual Plan | 7,964 | 250.226.
|
| (iii) New or Unusual Technology Barrier Equipment Conceptual Plan | 15,104 | 250.226.
|
| (iv) DWOP | 10,647 | 250.235.
|
| (v) Revised DWOP | 963 | 250.246.
|
| (vi) Combined Project Conceptual Plan/DWOP | 13,856 | 250.245.
|
| (vii) Supplemental DWOP | 9,626 | 250.247.
|
| (3) Application for Permit to Drill (APD; Form BSEE-0123) | $2,458 for initial applications only; no fee for revisions | § 250.410(d); § 250.513(b); § 250.1617(a).
|
| (4) Application for Permit to Modify (APM; Form BSEE-0124) | $145 | § 250.465(b); § 250.513(b); § 250.613(b); § 250.1618(a); § 250.1704(g).
|
| (5) New Facility Production Safety System Application for facility with more than 125 components | $6,312
A $16,610 additional fee will be charged if BSEE conducts a pre-production inspection of a facility offshore, and $8,638 for an inspection of a facility while in a shipyard
A component is a piece of equipment or ancillary system that is protected by one or more of the safety devices required by API RP 14C (as incorporated by reference in § 250.198) | § 250.842.
|
| (6) New Facility Production Safety System Application for facility with 25-125 components | $1,528
A $10,430 additional fee will be charged if BSEE conducts a pre-production inspection of a facility offshore, and $5,980 for an inspection of a facility while in a shipyard | § 250.842.
|
| (7) New Facility Production Safety System Application for facility with fewer than 25 components | $758 | § 250.842.
|
| (8) Production Safety System Application—Modification with more than 125 components reviewed | $704 | § 250.842.
|
| (9) Production Safety System Application—Modification with 25-125 components reviewed | $252 | § 250.842.
|
| (10) Production Safety System Application—Modification with fewer than 25 components reviewed | $107 | § 250.842.
|
| (11) Platform Application—Installation—Under the Platform Verification Program | $26,444 | § 250.905(l).
|
| (12) Platform Application—Installation—Fixed Structure Under the Platform Approval Program | $3,787 | § 250.905(l).
|
| (13) Platform Application—Installation—Caisson/Well Protector | $1,927 | § 250.905(l).
|
| (14) Platform Application—Modification/Repair | $4,518 | § 250.905(l).
|
| (15) New Pipeline Application (Lease Term) | $4,119 | § 250.1000(b).
|
| (16) Pipeline Application—Modification (Lease Term) | $2,392 | § 250.1000(b).
|
| (17) Pipeline Application—Modification (ROW) | $4,849 | § 250.1000(b).
|
| (18) Pipeline Repair Notification | $451 | § 250.1008(e).
|
| (19) Pipeline Right-of-Way (ROW) Grant Application | $3,223 | § 250.1015(a).
|
| (20) Pipeline Conversion of Lease Term to ROW | $275 | § 250.1015(a).
|
| (21) Pipeline ROW Assignment | $234 | § 250.1018(b).
|
| (22) 500 Feet from Lease/Unit Line Production Request | $4,527 | § 250.1156(a).
|
| (23) Gas Cap Production Request | $5,761 | § 250.1157(b).
|
| (24) Downhole Commingling Request | $6,722 | § 250.1158(a).
|
| (25) Complex Surface Commingling and Measurement Application | $4,718 | § 250.1202(a); § 250.1203(b); § 250.1204(a).
|
| (26) Simple Surface Commingling and Measurement Application | $1,595 | § 250.1202(a); § 250.1203(b); § 250.1204(a).
|
| (27) Voluntary Unitization Proposal or Unit Expansion | $14,678 | § 250.1303(d).
|
| (28) Unitization Revision | $1,042 | § 250.1303(d).
|
| (29) Application to Remove a Platform or Other Facility | $5,448 | § 250.1727.
|
| (30) Application to Decommission a Pipeline (Lease Term) | $1,328 | § 250.1751(a) or § 250.1752(a).
|
| (31) Application to Decommission a Pipeline (ROW) | $2,524 | § 250.1751(a) or § 250.1752(a). |