U.S Code last checked for updates: May 03, 2024
§ 2326g.
Beneficial use of dredged material; dredged material management plans
(a)
National policy on the beneficial use of dredged material
(1)
In general
(2)
Placement of dredged materials
(A)
In general
In evaluating the placement of dredged material obtained from the construction or operation and maintenance of water resources development projects, the Secretary shall consider—
(i)
the suitability of the dredged material for a full range of beneficial uses; and
(ii)
the economic and environmental benefits, efficiencies, and impacts (including the effects on living coral) of using the dredged material for beneficial uses, including, in the case of beneficial use activities that involve more than one water resources development project, the benefits, efficiencies, and impacts that result from the combined activities.
(B)
Calculation of Federal standard
(i)
Determination
(ii)
Reports
The Secretary shall submit to Congress—
(I)
a report detailing the method and all of the factors utilized by the Corps of Engineers to determine the Federal standard referred to in clause (i); and
(II)
for each evaluation under subparagraph (A), a report displaying the calculations for economic and environmental benefits and efficiencies from the beneficial use of dredged material (including, where appropriate, the utilization of alternative dredging equipment and dredging disposal methods) considered by the Secretary under such subparagraph for the placement or disposal of such material.
(C)
Omitted
(Pub. L. 116–260, div. AA, title I, § 125(a), Dec. 27, 2020, 134 Stat. 2636.)
cite as: 33 USC 2326g