U.S. CODE
Rulings
AD/CVD
Notices
HTSUS
U.S. Code
Regs
More
Ports
About
Updates
Apps
Larger font
Smaller font
SEARCH
Toggle Dropdown
Search US Code
Search Leg. Notes
Sort by Rank
Titles Ascending
Titles Descending
10 per page
25 Result/page
50 Result/page
U.S Code last checked for updates: Apr 01, 2026
All Titles
Title 10
Subtitle A
Part VI
Subpart B
Chapter 607
Subchapter I
§ 6284. Notification of cost ove...
§ 6286. Use of best practices fo...
§ 6284. Notification of cost ove...
§ 6286. Use of best practices fo...
U.S. Code
Notes
§ 6285.
Life-cycle cost estimates of certain atomic energy defense capital assets
(a)
In General
.—
The Secretary of Energy shall ensure that an independent life-cycle cost estimate under Department of Energy Order 413.3B (relating to program management and project management for the acquisition of capital assets), or a successor order, of each capital asset described in subsection (b) is conducted before the asset achieves critical decision 2 in the acquisition process.
(b)
Capital Assets Described
.—
A capital asset described in this subsection is an atomic energy defense capital asset—
(1)
the total project cost of which exceeds $100,000,000; and
(2)
the purpose of which is to perform a limited-life, single-purpose mission.
(c)
Independent Defined
.—
For purposes of subsection (a), the term “independent”, with respect to a life-cycle cost estimate of a capital asset, means that the life-cycle cost estimate is prepared by an organization independent of the project sponsor, using the same detailed technical and procurement information as the sponsor, to determine if the life-cycle cost estimate of the sponsor is accurate and reasonable.
(Added
Pub. L. 119–60, div. C, title XXXI, § 3111(a)
,
Dec. 18, 2025
,
139 Stat. 1434
.)