U.S Code last checked for updates: May 04, 2024
§ 47110.
Allowable project costs
(a)
General Authority.—
Except as provided in section 47111 of this title, the United States Government may pay or be obligated to pay, from amounts appropriated to carry out this subchapter, a cost incurred in carrying out a project under this subchapter only if the Secretary of Transportation decides the cost is allowable.
(b)
Allowable Cost Standards.—
A project cost is allowable—
(1)
(A)
if the cost necessarily is incurred in carrying out the project in compliance with the grant agreement made for the project under this subchapter, including any cost a sponsor incurs related to an audit the Secretary requires under section 47121(b) or (d) of this title and any cost of moving a Federal facility impeding the project if the rebuilt facility is of an equivalent size and type; or
(B)
if the cost is an incentive payment incurred in carrying out the project described in subparagraph (A) that is to be provided to a contractor upon early completion of a project, if—
(i)
such payment does not exceed the lesser of 5 percent of the initial construction contract amount or $1,000,000;
(ii)
the level of contractor’s control of, or access to, the worksite necessary to shorten the duration of the project does not negatively impact the operation of the airport;
(iii)
the contract specifies application of the incentive structure in the event of unforeseeable, non-weather delays beyond the control of the contractor;
(iv)
nothing in any agreement with the contractor prevents the airport operator from retaining responsibility for the safety, efficiency, and capacity of the airport during the execution of the grant agreement; and
(v)
the Secretary determines that the use of an incentive payment is likely to increase airport capacity or efficiency or result in cost savings as a result of shortening the project’s duration;
(2)
(A)
if the cost is incurred after the grant agreement is executed and is for airport development or airport planning carried out after the grant agreement is executed;
(B)
if the cost is incurred after June 1, 1989, by the airport operator (regardless of when the grant agreement is executed) as part of a Government-approved noise compatibility program (including project formulation costs) and is consistent with all applicable statutory and administrative requirements;
(C)
if the Government’s share is paid only with amounts apportioned under paragraphs (1) and (2) of section 47114(c) or section 47114(d)(3)(A) and if the cost is incurred—
(i)
after September 30, 1996;
(ii)
before a grant agreement is executed for the project; and
(iii)
in accordance with an airport layout plan approved by the Secretary and with all statutory and administrative requirements that would have been applicable to the project if the project had been carried out after the grant agreement had been executed; or
(D)
if the cost is for airport development and is incurred before execution of the grant agreement, but in the same fiscal year as execution of the grant agreement, and if—
(i)
the cost was incurred before execution of the grant agreement because the airport has a shortened construction season due to climatic conditions in the vicinity of the airport;
(ii)
the cost is in accordance with an airport layout plan approved by the Secretary and with all statutory and administrative requirements that would have been applicable to the project if the project had been carried out after execution of the grant agreement, including submission of a complete grant application to the appropriate regional or district office of the Federal Aviation Administration;
(iii)
the sponsor notifies the Secretary before authorizing work to commence on the project;
(iv)
the sponsor has an alternative funding source available to fund the project; and
(v)
the sponsor’s decision to proceed with the project in advance of execution of the grant agreement does not affect the priority assigned to the project by the Secretary for the allocation of discretionary funds;
(3)
to the extent the cost is reasonable in amount;
(4)
if the cost is not incurred in a project for airport development or airport planning for which other Government assistance has been granted;
(5)
if the total costs allowed for the project are not more than the amount stated in the grant agreement as the maximum the Government will pay (except as provided in section 47108(b) of this title);
(6)
if the cost is for a project not described in section 47102(3) for acquiring for use at a commercial service airport vehicles and ground support equipment owned by an airport that include low-emission technology, but only to the extent of the incremental cost of equipping such vehicles or equipment with low-emission technology, as determined by the Secretary; and
(7)
if the cost is incurred on a measure to improve the efficiency of an airport building (such as a measure designed to meet one or more of the criteria for being considered a high-performance green building as set forth under section 401(13) of the Energy Independence and Security Act of 2007 (42 U.S.C. 17061(13))) and—
(A)
the measure is for a project for airport development;
(B)
the measure is for an airport building that is otherwise eligible for construction assistance under this subchapter; and
(C)
if the measure results in an increase in initial project costs, the increase is justified by expected savings over the life cycle of the project.
(c)
Certain Prior Costs as Allowable Costs.—
The Secretary may decide that a project cost under subsection (b)(2)(A) of this section incurred after May 13, 1946, and before the date the grant agreement is executed is allowable if it is—
(1)
necessarily incurred in formulating an airport development project, including costs incurred for field surveys, plans and specifications, property interests in land or airspace, and administration or other incidental items that would not have been incurred except for the project; or
(2)
necessarily and directly incurred in developing the work scope of an airport planning project.
(d)
Relocation of Airport-Owned Facilities.—
The Secretary may determine that the costs of relocating or replacing an airport-owned facility are allowable for an airport development project at an airport only if—
(1)
the Government’s share of such costs will be paid with funds apportioned to the airport sponsor under section 47114(c)(1) or 47114(d);
(2)
the Secretary determines that the relocation or replacement is required due to a change in the Secretary’s design standards; and
(3)
the Secretary determines that the change is beyond the control of the airport sponsor.
(e)
Letters of Intent.—
(1)
The Secretary may issue a letter of intent to the sponsor stating an intention to obligate from future budget authority an amount, not more than the Government’s share of allowable project costs, for an airport development project (including costs of formulating the project) at a primary or reliever airport. The letter shall establish a schedule under which the Secretary will reimburse the sponsor for the Government’s share of allowable project costs, as amounts become available, if the sponsor, after the Secretary issues the letter, carries out the project without receiving amounts under this subchapter.
(2)
Paragraph (1) of this subsection applies to a project—
(A)
about which the sponsor notifies the Secretary, before the project begins, of the sponsor’s intent to carry out the project;
(B)
that will comply with all statutory and administrative requirements that would apply to the project if it were carried out with amounts made available under this subchapter; and
(C)
that meets the criteria of section 47115(d) and, if for a project at a commercial service airport having at least 0.25 percent of the boardings each year at all such airports, the Secretary decides will enhance system-wide airport capacity significantly.
(3)
A letter of intent issued under paragraph (1) of this subsection is not an obligation of the Government under section 1501 of title 31, and the letter is not deemed to be an administrative commitment for financing. An obligation or administrative commitment may be made only as amounts are provided in authorization and appropriation laws.
(4)
The total estimated amount of future Government obligations covered by all outstanding letters of intent under paragraph (1) of this subsection may not be more than the amount authorized to carry out section 48103 of this title, less an amount reasonably estimated by the Secretary to be needed for grants under section 48103 that are not covered by a letter.
(5)
Letters of intent.—
The Secretary may not require an eligible agency to impose a passenger facility charge under section 40117 in order to obtain a letter of intent under this section.
(6)
Limitation on statutory construction.—
Nothing in this section shall be construed to prohibit the obligation of amounts pursuant to a letter of intent under this subsection in the same fiscal year as the letter of intent is issued.
(7)
Partnership program airports.—
The Secretary may issue a letter of intent under this section to an airport sponsor with an approved application under section 47134(b) if—
(A)
the application was approved in fiscal year 2019; and
(B)
the project meets all other requirements set forth in this chapter.
(f)
Nonallowable Costs.—
Except as provided in subsection (d) of this section and section 47118(f) of this title, a cost is not an allowable airport development project cost if it is for—
(1)
constructing a public parking facility for passenger automobiles;
(2)
constructing, altering, or repairing part of an airport building, except to the extent the building will be used for facilities or activities directly related to the safety of individuals at the airport;
(3)
decorative landscaping; or
(4)
providing or installing sculpture or art works.
(g)
Use of Discretionary Funds.—
A project for which cost reimbursement is provided under subsection (b)(2)(C) shall not receive priority consideration with respect to the use of discretionary funds made available under section 47115 of this title even if the amounts made available under paragraphs (1) and (2) of section 47114(c) or section 47114(d)(3)(A) are not sufficient to cover the Government’s share of the cost of the project.
(h)
Nonprimary Airports.—
The Secretary may decide that the construction costs of revenue producing aeronautical support facilities are allowable for an airport development project at a nonprimary airport if the Government’s share of such costs is paid only with funds apportioned to the airport sponsor under section 47114(d)(3)(A) and if the Secretary determines that the sponsor has made adequate provision for financing airside needs of the airport.
(i)
Bird-Detecting Radar Systems.—
(1)
update Advisory Circular No. 150/5220–25 to specify which systems have been studied; and
(2)
within 180 days after such research is concluded, issue a final report on the use of avian radar systems in the national airspace system.
(Pub. L. 103–272, § 1(e), July 5, 1994, 108 Stat. 1264; Pub. L. 103–305, title I, § 115, Aug. 23, 1994, 108 Stat. 1579; Pub. L. 103–429, § 6(64), Oct. 31, 1994, 108 Stat. 4385; Pub. L. 104–264, title I, § 144, Oct. 9, 1996, 110 Stat. 3222; Pub. L. 106–181, title I, § 127, Apr. 5, 2000, 114 Stat. 76; Pub. L. 107–71, title I, § 119(a)(2), Nov. 19, 2001, 115 Stat. 628; Pub. L. 108–176, title I, §§ 145, 149(b), 159(c), Dec. 12, 2003, 117 Stat. 2504, 2505, 2511; Pub. L. 109–115, div. A, title I, § 176(b), Nov. 30, 2005, 119 Stat. 2427; Pub. L. 112–95, title I, §§ 111(c)(2)(A)(ii), 138, Feb. 14, 2012, 126 Stat. 18, 25; Pub. L. 115–254, div. B, title I, § 184(b), title V, § 539(n), Oct. 5, 2018, 132 Stat. 3234, 3371; Pub. L. 117–186, § 2, Oct. 10, 2022, 136 Stat. 2199.)
cite as: 49 USC 47110