§ 10245.
Site characterization; licensing
(a)
Site characterization
(b)
Licensing
(1)
Upon the completion of site characterization activities carried out under subsection (a), the Secretary shall submit to the Nuclear Regulatory Commission an application for construction authorization for a repository at such site.
(2)
The Nuclear Regulatory Commission shall consider an application for a construction authorization for a repository or monitored retrievable storage facility in accordance with the laws applicable to such applications, except that the Nuclear Regulatory Commission shall issue a final decision approving or disapproving the issuance of a construction authorization not later than 3 years after the date of the submission of such application.
(Pub. L. 97–425, title IV, § 405, as added Pub. L. 100–202, § 101(d) [title III], Dec. 22, 1987, 101 Stat. 1329–104, 1329–121; Pub. L. 100–203, title V, § 5041, Dec. 22, 1987, 101 Stat. 1330–246.)
cite as: 42 USC 10245